The first phase of the project is located near the ball fields on Turtle Lane just off Harbor Road. This entails laying the force main which will follow the Ti Haul Trail to Bay Road, cross the LaPlatte River just north of the Bay Road Bridge and then follow Bay Road north to Turtle Lane and the Crown Road wastewater treatment facility.

Work Hours:

Construction activities will be restricted to the daytime hours of 7AM and 5PM, Monday through Friday.  No weekend work, or work outside the standard hours is currently planned.  If this is necessary, ECI will need to request this in advance and get approval from the Town. 

CONSTRUCTION ACTIVITIES:

​

NOTE: Bay Road will not be opening for use until mid-December, as the contractor needs to complete the boring and pull the pipe through. If work is stopped now there is a likelihood that the boring hole will collapse over the winter and all the work completed so far will be lost.  This continued closure will not impact winter road maintenance activities.  Please see weekly updates below:  

​

November 30--December 4: 

​​

Bay Road will remain closed, and local traffic only will be able to access the road.  The closure is between Spinnaker Lane and the bridge crossing the LaPlatte River. Bay Road will be sporadically one way, depending on which areas the crew will be preparing for paving.  There will be one lane with alternating traffic and flagger assistance. 

​​

The sign on Route 7 will read: "Bay Road Closed at Spinnaker Lane.'

 

There will be an emergency lane for emergency response vehicles. 

 

To access Shelburne Farms and Shelburne Point use Harbor Road.

 

The Ti Haul Trail is currently closed for drilling activities and will remain closed for the winter season.

​​​​​​​​​

A drill drew will continue with the LaPlatte River pull reaming.  

​

A civil crew will undertake restoration and Trail maintenance work.  

​​​​
Once the road closure is active, access to the boat launch or Shelburne Farms will only be available from Harbor Road. There will be no access to these locations from Bay Road while the road closure is active. ​

Trenchless Work

Monday, 6/8/26 – Monday,11/23/26

Pavement Repairs

Monday, 11/2/26 – Wed 11/11/26

Open Cut

Monday, 8/10/26 – Wednesday, 5/12/27

Site Clean-up

Monday, 5/10/27 – 5/14/27

Logo, Town of Shelburne, VT

CONTACT US
Town of Shelburne
5420 Shelburne Road
Shelburne, VT 05482
Phone: 802-985-5110
Fax: 802-985-9550

Privacy Policy | Terms and Conditions

  • Instagram
  • Facebook

Shelburne Wastewater Treatment Facility Modernization Project © All Rights Reserved

bottom of page